When workers opened a wall at Augusta’s Appleby Branch Library to prepare for an elevator, they found old knob-and-tube wiring. Engineers determined that sections of it still carried power, according to the renovation scope in the commission packet. The discovery is the biggest reason city staff are now asking for more money.

Item 41 on the Dec. 1 commission agenda asks for $599,600.27 in extra renovation work and $50,000 in additional contingency, or $649,600.27 if both are approved. Staff propose using available collections from Augusta’s seventh special-purpose local sales tax. The item is on the regular agenda; it is a request, not an approved expenditure.

Electrical work is $468,985, including replacement wiring and the labor, permits, demolition and repairs that go with installing it. The itemized request also lists $64,438.94 to restore hardwood floors, $59,176.33 to replace shutters, and $7,000 for design work. Staff say the original positions of the elevator and restroom had to shift to accommodate beams.

The contingency is separate from those identified costs. Its purpose is to cover additional surprises, not work stated to have already occurred. The agenda does not set a reopening date.