The Nixon data-center proposal is back on Augusta’s public-meeting calendar. The current special-called Planning Commission agenda schedules its two applications for Monday, Nov. 23, at 2 p.m.
Use the room on the current city agenda and city calendar: Augusta Commission Chambers, Room 260, on the second floor of the Municipal Building, 535 Telfair St.
Two applications, one proposed development
Case Z-26-18 seeks to rezone approximately 383 acres from agricultural, general-business and heavy-industrial classifications to the DC data-center district. Case SE-26-22 seeks a special exception under Section 22-4(A) for the data center.
The agenda identifies 3 G Investments LLC as applicant for the Nixon Trusts and lists 1538 and 1550 Four H Club Road and 3806 Mike Padgett Highway. These are applications before the Planning Commission, not an announcement that the project has been approved.
How to participate
Interested people may attend and present comments. The agenda also directs people submitting written or verbal comments to Planning & Development at 706-821-1796 during business hours.
Requests for disability accommodations or language translation should reach that department at least 48 hours before the meeting. The reviewed Nixon agenda does not specify a speaker time limit.
What changed since the earlier notice
GCG’s Nov. 3 report described the earlier Nov. 2 agenda, which marked the applications postponed until December at the applicant’s request. The newer special-called agenda now puts them on Nov. 23. Readers planning to attend should use the current notice, not the earlier December expectation.
The separate state regional-review record also deserves a careful reading. Checked Nov. 18, the Georgia Department of Community Affairs summary for Nixon Technology Center still says “Request for Comments Made,” gives Nov. 29 as the projected process-completion date and displays no regional finding. A projected date is not a completed review or approval.
The developer’s regional-review filing describes approximately 388 acres and 3.34 million square feet. That acreage differs from the approximately 383 acres in the zoning agenda; the two descriptions should not be silently treated as identical.
Not the December QTS hearing
Nixon’s zoning meeting is separate from the Dec. 3 state air-permit hearing concerning the QTS ATL3 campus proposed at 2883 Gordon Highway. That hearing takes place at 535 Telfair Street, Suite 260, from 6 to 7:30 p.m. Different projects and different regulatory questions are involved. A comment intended for one proceeding should not be assumed to count in the other.