A temporary lot for Columbia County’s White Oak data-center construction would have room for 3,416 parked vehicles and a new entrance off U.S. 221. The public filing shows where construction traffic could turn off the highway. It does not show that the entrance has been approved.
The initial state filing calls the proposal Project JGK–Temporary Logistics Yard A. It covers 159 acres at 870 Progress Drive and includes staging areas and a construction office as well as the parking lot. Columbia County submitted the forms on Nov. 16, listing Turner Construction as the developer on behalf of Kinetic Infrastructure Solutions. The signed agreement covered earlier by Garden City Gossip identifies Kinetic as a Google subsidiary.
What the road filing says
The transportation portion of the filing proposes a driveway connection to U.S. 221, also called Appling Harlem Road. It says other corridor upgrades are pending review by the Georgia Department of Transportation. The form indicates that a traffic study has been done and that transportation improvements are needed. It does not include the study or identify the final road work.
The form gives a traffic estimate of 1,596. Its question refers to peak-hour trips and permits an alternative measure, but the answer does not specify the counting interval or method. That number is not a reported traffic count, and the 3,416 parking spaces do not tell drivers how many vehicles would arrive at a shift change.
A separate review from mass grading
On Nov. 18, the state’s Yard A record recorded a determination that the proposal warrants regional review. The fields for completeness certification, a request for comments and a regional finding were blank when checked Nov. 24. A decision to review the proposal is not approval.
The yard filing expressly links this proposal to the earlier JGK mass-grading review. The state marks that separate review completed and dates its regional finding July 22. That entry does not resolve the new entrance. Nor is the temporary yard the permanent data-center footprint. The filing lists September 2027 for completion of this phase and September 2035 for the overall project, both as estimates.
The records that would answer the next question for drivers are the traffic study and any GDOT driveway decision: where the turn would go, when traffic would be heaviest, what road work would be required and who would pay for it. Those answers are not in the public state forms.